Nordex completes turbine installation at the 21.6 MW Honkajoki wind farm in Finland

View from the top of recently commissioned Honkajoki wind farm in South-Western Finland

The nine-turbine facility, which was developed for Finnish wealth management company Taaleritehdas, is the first in the country to feature the company’s N117 2.4MW machines.

Honkajoki, which is now grid-connected, is also the first project under a framework contract signed with Taaleritehdas in June 2012 providing for the delivery of up to 111 turbines.

Nordex management board member Lars Bondo Krogsgaard said: “This marks a real success for our new activities in Finland and creates an excellent basis for future projects with Taaleritehdas.”

The early completion of Honkajoki allowed Taaleritehdas to generate energy earlier than anticipated and tap into the “early bird premium” for wind power generated before 2016.

Taaleritehdas director of wind energy businesses Taamir Fareed added: “The remarkable performance of the Nordex team in its first project in Finland provides a very good basis for our future co-operation, in which we will be installing more Nordex turbines in Finland.”